An address in Kensington-Cedar Cottage, Vancouver, zoned CD-1 (738) (Comprehensive Development). 17 building permits are on file, most recently “Sub permit of BP-2019-02299 - BP-2020-01661- Building A, 3588 Hull - To construct a 4-sto…” (issued 3 March 2021). The City's 2026 assessed value is $46,863,000.

Zoning
CD-1 (738) · Comprehensive Development
Neighbourhood
Kensington-Cedar Cottage
Permits on file
17
Assessed value (2026)
$46,863,000
Owner names are not part of the City's open data and are never shown. Sold prices are not municipal open data and are not shown. Assessed value is the City's estimate for property tax, not a sale price.
Plan of the block around 3588 Hull St, drawn from City open data, with the address marked
Parcel outlines, street centrelines and address points from the City of Vancouver's open data, drawn by Permit Gopher; not an official plan. Contains information licensed under the Open Government Licence – Vancouver.

Neighbourhood profile

From the 2021 Census, for the small area around this address that Statistics Canada calls a dissemination area (59150424, 883 people). Statistics Canada draws these areas; they are not the City's neighbourhoods.

People
883
Households
320
Median age
41.6
Median household income (2020)
$84,000
Own their home
53%
Vancouver: 45%
Average household size
2.5
Under 15
17%
65 and over
22%
Income in the 2021 Census is for the year 2020. Statistics Canada rounds counts and does not publish some figures for very small areas.

Permit history

  1. 2021-03-03 Sub permit of BP-2019-02299 - BP-2020-01661- Building A, 3588 Hull - To construct a 4-storey market rental residential apartment building (21 dwelling units) Stage #1 - Partial demolition and relocation of the existing heritage single family house - issued 2020-01-13 Stage #2 - Construction of the existing heritage single family house and excavation and structure up to grade of the new development - issued 2020-01-29 Stage #3 - All structural work up to roof - issued 2020-02-18 Stage #4 - Full Construction - issued 2021-03-02 Refer to BP-2019-02299 for site work, below-grade facilities, and common parkade. Refer to BP-2019-02299 for Rev. #1 REVISION #2 (Aug 10/22): Revision to Stage #4 - Full Construction related to DP-2021-00790, A.Min
    no contractor listed
    Issued
  2. 2021-03-03 Sub permit of BP-2019-02299 - Building H, 3560 Hull St - To relocate and alter the existing two-storey heritage building containing 1 dwelling unit. Stage #1 - Partial demolition and relocation of the existing heritage single family house - issued 2020-01-13 Stage #2 - Construction of the existing heritage single family house and excavation and structure up to grade of the new development - issued 2020-01-29 Stage #3 - All structural work up to roof - issued 2020-02-18 Stage #4 - Full Construction - issued 2021-03-02 Refer to BP-2019-02299 for site work, below-grade facilities, and common parkade. Refer to BP-2019-02299 for Rev. #1 REVISION #2 (Aug 10/22): Revision to Stage #4 - Full Construction related to DP-2021-00790, A.Min
    no contractor listed
    Issued
  3. 2021-03-03 Sub permit of BP-2019-02299 - Building E, 2030 E 20th Ave. - To construct a 5-storey market rental residential townhouse building containing 10 dwelling units. (First storey is the common parkade.) Stage #1 - Partial demolition and relocation of the existing heritage single family house - issued 2020-01-13 Stage #2 - Construction of the existing heritage single family house and excavation and structure up to grade of the new development - issued 2020-01-29 Stage #3 - All structural work up to roof - issued 2020-02-18 Stage #4 - Full Construction - issued 2021-03-02 Refer to BP-2019-02299 for site work, below-grade facilities, and common parkade. Rev.#1 - Correction of addresses for individual buildings to match addressing notifications and drawings - K.Anderson June 18/21 REVISION #2 (Aug 10/22): Revision to Stage #4 - Full Construction related to DP-2021-00790, A.Min - Raised bottom of window box buildouts by 2 feet.
    no contractor listed
    Issued
  4. 2021-03-03 Sub permit of BP-2019-02299 - Building D, 2070 E 20th Ave. - To construct a 5-storey market rental residential townhouse building containing 8 dwelling units. (First storey is the common parkade.) Stage #1 - Partial demolition and relocation of the existing heritage single family house - issued 2020-01-13 Stage #2 - Construction of the existing heritage single family house and excavation and structure up to grade of the new development - issued 2020-01-29 Stage #3 - All structural work up to roof - issued 2020-02-18 Stage #4 - Full Construction - issued 2021-03-02 Refer to BP-2019-02299 for site work, below-grade facilities, and common parkade. Rev.#1 - Correction of addresses for individual buildings to match addressing notifications and drawings - K.Anderson June 18/21 REVISION #2 (Aug 10/22): Revision to Stage #4 - Full Construction related to DP-2021-00790, A.Min - Raised bottom of window box buildouts by 2 feet.
    no contractor listed
    Issued
  5. 2021-03-03 Sub permit of BP-2019-02299 - BP-2019-05295 - Building C, 2050 E 20th Ave. - To construct a 4-storey market rental residential townhouse building containing 14 dwelling units. Stage #1 - Partial demolition and relocation of the existing heritage single family house - issued 2020-01-13 Stage #2 - Construction of the existing heritage single family house and excavation and structure up to grade of the new development - issued 2020-01-29 Stage #3 - All structural work up to roof - issued 2020-02-18 Stage #4 - Full Construction - issued 2021-03-02 Refer to BP-2019-02299 for site work, below-grade facilities, and common parkade. Rev.#1 - Correction of addresses for individual buildings to match addressing notifications and drawings - K.Anderson June 18/21 REVISION #2 (Aug 10/22): Revision to Stage #4 - Full Construction related to DP-2021-00790, A.Min
    no contractor listed
    Issued
  6. 2021-03-03 Sub permit of BP-2019-02299 - Building B - 3592 Hull St. - To construct a 4-storey market rental residential townhouse building containing 14 dwelling units. Stage #1 - Partial demolition and relocation of the existing heritage single family house - issued 2020-01-13 Stage #2 - Construction of the existing heritage single family house and excavation and structure up to grade of the new development - issued 2020-01-29 Stage #3 - All structural work up to roof - issued 2020-02-18 Stage #4 - Full Construction - issued 2021-03-02 Refer to BP-2019-02299 for site work, below-grade facilities, and common parkade. Rev.#1 - Correction of addresses for individual buildings to match addressing notifications and drawings - K.Anderson June 18/21 REVISION #2 (Aug 10/22): Revision to Stage #4 - Full Construction related to DP-2021-00790, A.Min - Raised bottom of window box buildouts by 2 feet.
    no contractor listed
    Issued
  7. 2020-01-29 This permit has been issued for all site work and below grade facilities including one level of common underground parking for the proposed development: To relocate, rehabilitate, and designate the existing two-storey heritage building, to develop this site with a Multiple Dwelling comprising a total of 68 secured market rental dwelling units, over two levels of parking underground, having vehicular access from East 20th Av. · $33,000,000
    no contractor listed
    Issued
  8. 2020-01-09 To demolish the existing one family dwelling building ($15,000) on this site by means of deconstruction. Note: Recycling requirement: 75% of non-hazardous construction waste. OK for SIPS as per City staffo District Building Inspector 24 hours in advance of demolition by calling 3-1-1 or [contact removed] outside Vancouver. · $15,000
    no contractor listed
    Issued
  9. 2019-10-15 To demolish the existing one family dwelling building ($15,000) on this site by means of deconstruction. Note: Recycling requirement: 75% of non-hazardous construction waste. OK for SIPS as per City staffo District Building Inspector 24 hours in advance of demolition by calling 3-1-1 or [contact removed] outside Vancouver. · $15,000
    applicant withheld (individual)
    Issued
  10. 2019-10-11 To demolish the existing one family dwelling building ($15,000) on this site by means of deconstruction. Note: Recycling requirement: 75% of non-hazardous construction waste. OK for SIPS as per City staffo District Building Inspector 24 hours in advance of demolition by calling 3-1-1 or [contact removed] outside Vancouver. · $15,000
    applicant withheld (individual)
    Issued
  11. 2019-10-11 To demolish the existing one family dwelling building ($15,000) on this site by means of deconstruction. Note: Recycling requirement: 75% of non-hazardous construction waste. OK for SIPS as per City staffo District Building Inspector 24 hours in advance of demolition by calling 3-1-1 or [contact removed] outside Vancouver. · $15,000
    applicant withheld (individual)
    Issued
  12. 2019-10-07 Salvage and abatement permit only for DB-2019-03908 and to be completed under the supervision of a registered professional. This permit does not authorize demolition, deconstruction or construction work, and to be completed under the supervision of a registered professional.
    applicant withheld (individual)
    Issued
  13. 2019-08-30 Interior alterations to allow salvage of non-structural building components prior to or during abatement work and removal of non-structural hazardous materials in this existing single family dwelling building. Note: QP is Ramin Hamidnejad of Kinetic OHS Services Ltd., [contact removed] Work under this permit is limited to salvage and abatement. No other demolition work is permitted. · $15,000
    no contractor listed
    Issued
  14. 2019-08-30 Interior alterations to allow salvage of non-structural building components prior to or during abatement work and removal of non-structural hazardous materials in this existing single family dwelling building. Note: QP is Ramin Hamidnejad of Kinetic OHS Services Ltd., [contact removed] Work under this permit is limited to salvage and abatement. No other demolition work is permitted. · $15,000
    no contractor listed
    Issued
  15. 2019-08-30 Interior alterations to allow salvage of non-structural building components prior to or during abatement work and removal of non-structural hazardous materials in this existing single family dwelling building. Note: QP is Ramin Hamidnejad of Kinetic OHS Services Ltd., [contact removed] Work under this permit is limited to salvage and abatement. No other demolition work is permitted. · $15,000
    applicant withheld (individual)
    Issued
  16. 2019-08-30 Interior alterations to allow salvage of non-structural building components prior to or during abatement work and removal of non-structural hazardous materials in this existing single family dwelling building. Note: QP is Ramin Hamidnejad of Kinetic OHS Services Ltd., [contact removed] Work under this permit is limited to salvage and abatement. No other demolition work is permitted. · $15,000
    no contractor listed
    Issued
  17. 2019-04-02 This permit is for exploratory work as identified in items #1 to 4. 1) Removal of interior drywall consisting of a single (max 2'0" high) horizontal band around the original perimeter walls of this existing one family dwelling at mid-height window level to confirm locations of original stud walls and opening. 2) Removal of interior drywall consisting of vertical strips as identified in the drawings provided (max 2'0" wide) from floor height to ceiling height in locations of discovered original framed openings to confirm original construction assemblies and opening dimensions. 3) Removal of interior ceiling as identified by the drawings provided, no greater than 2'0' by 2'0" per City staff(max 4 cut-outs), to confirm existence, location and assembly of original floor and roof structural elements. 4) Removal of exterior stucco, no greater than 2'0' by 2'0" per City staff(max 4 cut-outs), if interior investigations require further confirmation. This permit does not include: a) The removal of hazardous and non-hazardous materials; and b) The removal of non-structural building components (i.e. kitchen, bathroom, and etc.); and c) Interior and exterior alterations to this existing One Family Building on this site. Note: - Separate Permits and Approvals will be required for interior and exterior alterations and to relocate this existing building. - Any removal of exterior stucco is to be repaired to match the existing conditions unless further permits have been obtained to alter the exterior. - This permit is for exploratory work only. Any unauthorized work on this site, existing or otherwise, is neither recognized nor approved and may be subject to enforcement action. · $5,000
    Performance Builders Ltd
    Issued

The City of Vancouver publishes permits when they are issued and does not show whether the work was completed, so every Vancouver permit shows as Issued with its issue date.

Email alerts and sign-up aren't available yet. Everything on these pages is free to use without an account. Questions: [email protected]

Recent permits in Kensington-Cedar Cottage

1641 E 37TH Av
To demolish the existing single detached house ($40,000) on this site - declared non rental 75% green demo Demo to grade only. No soil disturbance or excavation of soil other than that which is incidental to the demolition is permitted under this permit. This permit is subject to the Green Demolition Bylaw (11023). Pre-1950 homes require recycling of a minimum 75 percent of non-hazardous construction materials, and pre-1940 homes with character will require a minimum 90% recycling of non-hazardous construction materials. In addition, Pre-1910 homes and pre-1950 heritage homes require demolition by means of deconstruction, resulting in the salvage of at least 3 tonnes of wood. Demo: N. Parsad - 1167245 BC Ltd QP: MCA Environmental Consulting Inc. (Tarlochan Sunar ) · no contractor listed
2026-10-28
1641 E 37TH Av
*****PART 5***** To construct a three-storey four-unit Multiple Dwelling "Multiplex" building with four surface parking spaces in the rear yard, having vehicular access from the lane. VBBL 2025 - NFPA 13D · Kang Bros Holdings Ltd
2026-10-28
4375 Ross St
Exterior alterations to add a new roof cover over the existing deck at the rear of the second floor of this existing single detached house on this inside with lane site as approved by the Board of Variance Appeal Z36309 dated March 10, 2026, thereby overturning the decision of the Director of Planning and relaxing the overall floor area to 2,593sf. Related to Issued DP-2025-00980 Full-height privacy screen to be installed on the south elevation. · no contractor listed
2026-10-26