1385 W 8th Av, Vancouver

An address in Fairview, Vancouver, zoned FM-1 (Residential). 23 building permits are on file, most recently “Unit #105 - 1st floor Interior alterations to provide improvements for this existing offi…” (issued 18 September 2026). The City's 2026 assessed value is $43,396,000.

Zoning
FM-1 · Residential
Neighbourhood
Fairview
Permits on file
23
Assessed value (2026)
$43,396,000
Owner names are not part of the City's open data and are never shown. Sold prices are not municipal open data and are not shown. Assessed value is the City's estimate for property tax, not a sale price.
Plan of the block around 1385 W 8th Av, drawn from City open data, with the address marked
Parcel outlines, street centrelines and address points from the City of Vancouver's open data, drawn by Permit Gopher; not an official plan. Contains information licensed under the Open Government Licence – Vancouver.

Neighbourhood profile

From the 2021 Census, for the small area around this address that Statistics Canada calls a dissemination area (59153132, 1,360 people). Statistics Canada draws these areas; they are not the City's neighbourhoods.

People
1,360
Households
715
Median age
47.2
Median household income (2020)
$113,000
Own their home
76%
Vancouver: 45%
Average household size
1.9
Under 15
10%
65 and over
23%
Income in the 2021 Census is for the year 2020. Statistics Canada rounds counts and does not publish some figures for very small areas.

Permit history

  1. 2026-09-18 Unit #105 - 1st floor Interior alterations to provide improvements for this existing office tenant on the 1st floor (#105) of this existing commercial building on this site. Scope of work; demo and construction of partition walls to alter layout. Electrical to suit. District Building Inspector to determine if a Special Sprinkler Inspection is required. · $75,000
    no contractor listed
    Issued
  2. 2026-07-02 #530 - 5th floor Interior alterations to provide tenant improvements to this existing general office on the 5th floor (#530) of this existing commercial building on site. Scope of work: Selective demo to alter layout and create an open space area. Building Sprinklered – Building inspector to determine on site if a separate sprinkler permit is required. Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · $40,000
    Altek Construction Ltd
    Issued
  3. 2025-01-20 #540 - 5th floor Interior alterations to provide improvements for a new office tenant on the 5th floor (#540) of this existing commercial building on this site. Scope of work; demo partition walls to select areas to alter layout. Electrical, Plumbing, & Sprinklers to suit. See BP-2024-04848 for demising work Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · $305,000
    Epic Spaces Inc
    Issued
  4. 2025-01-07 #310 - 3rd floor (combining units #310 and #360) Interior alterations to the 3rd floor to combine units #310 & #360 (retain unit #310) and provide improvements in this existing commercial building on this site. Scope of work: remove demising wall, demo and construction of partition walls to select areas in the expanded areas, and patch, paint and repair to match existing ceiling, flooring & walls. District Building Inspector to determine if a Special Sprinkler Inspection is required. OK for F/R as per City staffr required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing) · $75,000
    Enduro Construction Ltd
    Issued
  5. 2024-12-16 5TH FLOOR - #540 demising into #540 and #530 Interior alterations to the 5th floor to demise this existing full floor office space (unit #540) into two units ( to be #540 and #530) in this existing commercial building on this site. Scope of work: demo to select areas ,construct demising walls.,& add 3 new doors to #540. Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · $70,000
    Enduro Construction Ltd
    Issued
  6. 2024-03-15 #290 - 2nd floor Interior alterations to remove partitions to this vacant office space on the 2nd floor (#290) to prepare for leasing in this existing commercial building on this site. Scope of work: select demo, patch & paint walls, repair t-bar ceiling and tiles where required, Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · $30,000
    Enduro Construction Ltd
    Issued
  7. 2023-11-03 #350 - 3rd Floor Interior alterations to provide tenant improvement to a new tenant on the 3rd floor (#350) of this existing commercial building on site. Scope of work: Construct prefabricated office partitions, new bulkhead and electrical work. TENANT: Pacific Salmon Foundation Building Sprinklered – Building inspector to determine on site if a separate sprinkler permit is required. Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · $10,000
    Avid Contracting Ltd
    Issued
  8. 2022-12-20 Unit #310 - 3rd Floor Interior alterations to provide improvements for this existing office tenant at office unit #310 on the 3rd floor of this commercial building on this site. OK for field review per City staff. Scope of Work: - Construct new interior partition wall to alter layout for a new office. Demolish partition walls to create a new meeting room. Electrical and sprinkler work Note: No energy trigger required; BOMA BEST building Okay for Field Review by N. Jalalkamali November 14, 2022. · $35,000
    Counterpoint Interiors Inc
    Issued
  9. 2022-11-16 #111 - 1st floor Interior alterations to provide improvements for a new office tenant on the 1st floor (#111) in this existing commercial building on this site. Scope of work: remove/construct partition walls, doors, ceiling work, millwork, finishes, lighting, electrical, plumbing, mechanical and sprinkler work. · $1,230,000
    Govan Brown Ltd
    Issued
  10. 2022-04-21 #610 - 6th floor Interior alterations to provide improvements for a new office tenant on the 6th floor (#610) in this existing commercial building on this site. Scope of work: remove/construct partition walls, doors, flooring, millwork, finishes, electrical and sprinkler work. TENANT: iCreative Service Inc. E2 - Retrofit Path: BOMA BESt (Path 1) - No Additional Upgrades Req'd Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). All energy upgrades will be checked during inspections stage. It is the applicant’s responsibility to identify and note all required upgrades including energy upgrades on their BP drawings at BP stage. · $70,000
    Matra Construction Inc
    Issued
  11. 2021-07-22 #600 - 6th floor Interior alterations to provide improvements for this new office tenant on the 6th floor (#600) of this existing commercial building on this site. Scope of Work: Demo and construct interior walls and doors to reconfigure space. Electrical, plumbing and sprinkler to suit. · $100,000
    Humphries Construction Group Ltd
    Issued
  12. 2020-10-01 Lobby area Exterior alterations to replace existing lobby glazing with new curtain wall system and relocate entrances, and interior alterations to provide improvements to the lobby area on the ground floor of this existing commercial building. Scope of work includes updating the existing exterior plaza. OK for field review as per City staff · $650,000
    no contractor listed
    Issued
  13. 2020-06-10 #117 Interior alterations to expand existing amenity gym including change room for existing tenants' use only in unit #117 - 1385 W 8th Av in this existing commercial building. OK for field review as per City staffion of partitions, construction of new partitions, new fixtures, millwork, ceilings, mechanical, lighting and sprinkler work · $380,000
    no contractor listed
    Issued
  14. 2019-11-14 #111 - 1st Floor Interior alterations to provide tenant improvements on the 1st floor (#111) of this existing mixed use building. Scope of work: construct a new partition wall and a new door and sidelight to match existing, electrical and sprinkler work. Building Sprinklered – Separate sprinkler permit required for proposed sprinkler work OK for Field Review Oct 28, 2019 Processed Thru FIT. L2 - HVAC - Clean and Balance all Air Systems (per City staff.7.2.3.2 of ASHRAE 90.1-2016)\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t · $10,000
    Matra Construction Inc
    Issued
  15. 2019-09-06 #105 - 1st Floor Interior alterations to provide tenant improvements for this existing office tenant on the 1st floor (#105) in this existing mixed use building. Scope of work: remove millwork, furniture and construct new partition walls, doors and glazing for new offices, ceiling work, lighting, finishes, voice and data and electrical work. TENANT: The Mortgage Group Building Sprinklered – Building inspector to determine on site if a separate sprinkler permit is required. OK for Field Review - Aug 26, 2019 Processed Thru FIT L2 - Lighting - Upgrade to incorporate Automatic Lighting Shutoff (per City staff.4.1.1 of ASHRAE 90.1-2016)\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t\t · $40,000
    Matra Construction Inc
    Issued
  16. 2019-03-28 #355 Interior alteration to provide tenant improvement in suite #355 of this existing commercial building on this site. Okay for field review as per City staff: L2 - Lighting - Upgrade to incorporate Automatic Lighting Shutoff (per City staff.4.1.1 of ASHRAE 90.1 - 2010) · $100,000
    no contractor listed
    Issued
  17. 2018-11-30 #111 - Ground Floor Interior alterations only to provide a new partition wall to create two new office rooms in this existing General Office tenant on the ground floor (#111) at this existing commercial building. Scope of work: new partition wall, finishes TENANT: Zymeworks Inc. OK for field review as per City staff. No energy upgrade required. BOMA BESt building. Related to Special Sprinkler Permit No. IA-2018-01735. · $20,000
    Matra Construction Inc
    Issued
  18. 2018-08-29 #540 Interior alterations to provide improvements for this existing office tenant at office unit #540 on the 5th floor of this commercial building on this site. OK for field review per City staff. Scope of Work: - construct new interior partition walls and doors to alter layout for new offices Note: No energy trigger required; BOMA BESt building · $130,000
    Matra Construction Inc
    Issued
  19. 2018-08-28 #400 - 4th floor Interior alterations to provide improvements for this existing full floor General Office tenant on the 4th floor (#400) of this existing commercial building. Scope of work: alter select areas; demo/construct parition walls so alter reception, & meeting room. relocate recessing light fixtures to suite new layout , add one recessed light, provide power and data outlets for new open area workstations. Tenant: Klein Lawyers LLP & David A. Klein Law Corporation. OK for field review as per City staff. No energy upgrade required. BOMA BESt building. Related to IA-2018-01197. · $50,000
    Fusion Project Management Ltd
    Issued
  20. 2017-11-09 # 310 Interior alterations to provide improvements for new office tenant in unit #310 on the 3rd floor of this existing commercial building. BOMA BESt building · $120,000
    no contractor listed
    Issued
  21. 2017-10-10 #310 & #360-3rd floor Interior alterations to existing office tenant (#360) and to expand office unit #310 into a portion of office unit #360 on the 3rd floor of this existing commercial building on this site. Scope of work: construct new demising wall, new partition wall, existing partition wall to receive baffle above t-bar ceiling complete with smoke separation, remove millwork, new finishes, electrical and sprinkler work. Separate permit(s) and ASHRAE checklist will be required for any future tenant improvements to suite #310. TENANT: Diabetes Canada OK for field review per City staff. Energy trigger chosen; L2 - HVAC - Clean and balance all Air Systems (per City staff.7.2.3.2 of ASHRAE 90.1-2010) · $40,000
    Matra Construction Inc
    Issued
  22. 2017-07-17 #290-2nd floor Interior alterations to provide tenant improvements for the existing office tenant at unit #290 on the second floor of this existing commercial building on this site. Scope of work: construct new partition walls, new doors to create two new offices and one new copy room, new lighting, electrical and sprinkler work. TENANT: iCreative (Lean Sensei) OK for field review per City staff. Note: No energy trigger required BOMA BESt building. · $44,000
    Matra Construction Inc
    Issued
  23. 2017-07-05 #111 - 1st floor Interior alterations only to remove non-loadbearing walls to open up an office for the existing tenant at this existing general office on the ground floor of this existing commercial buidling on this site. Ok for field review per City staff: BOMA BESt Building · $2,000
    no contractor listed
    Issued

The City of Vancouver publishes permits when they are issued and does not show whether the work was completed, so every Vancouver permit shows as Issued with its issue date.

Email alerts and sign-up aren't available yet. Everything on these pages is free to use without an account. Questions: [email protected]

Recent permits in Fairview

1126 W 13TH Av
To replace the structural posts in the front covered area of this existing multiple dwelling building. OK to process as DTI as per City staff · no contractor listed
2026-11-05
1401 W 8TH Av
#300-1401 W 8th Avenue Interior alterations to provide tenant improvements to this existing Radio Communication Station to add one meeting room within unit #300 on the 3rd level of this existing commercial building on this site. Okay for FR as per City staff · Multigroup Enterprise Corp
2026-11-05
1650 W 1ST Av
Exterior alterations for targeted building envelope repairs to the south roof deck membrane in this existing multiple dwelling building on this site. The scope includes to remove and replace the sanitary piping on this roof deck. Ok for Field review per City staff · no contractor listed
2026-11-04
Something wrong on this page? Tell us and we'll check it against the City's records.