Help: This address page
What this page does
This page shows what the city's open data records for one address: the zoning and what it means, the neighbourhood, every building permit on file and, where the city publishes it, the assessed value. It also shows the property on the city's aerial photo or a drawn plan, a 2021 Census profile of the small area around it, and recent permits nearby. Free, no account. Owner names and sold prices are never shown; the assessed value is the city's estimate for property tax, not a sale price.
How to use it
- Read the top lines for the summary: zoning, neighbourhood, number of permits and assessed value.
- Use + and − on the plan to zoom in and out.
- Scroll to Permit history for every permit on the lot: what was done, when, by which company, the value and the status.
- Click a nearby permit to open its address, or This week's permit digest → for the whole city.
- Something looks wrong? Use the Tell us link at the bottom and we'll check it against the city's records.
1275 Haro St, Vancouver
An address in West End, Vancouver, zoned RM-5B (Residential). 2 building permits are on file, most recently “Interior alterations to provide modernization of existing two elevators to allow for elev…” (issued 22 February 2021). The City's 2026 assessed value is $33,622,000.
Neighbourhood profile
From the 2021 Census, for the small area around this address that Statistics Canada calls a dissemination area (59153669, 347 people). Statistics Canada draws these areas; they are not the City's neighbourhoods.
Permit history
-
2021-02-22
Interior alterations to provide modernization of existing two elevators to allow for elevator recall in this existing 10-storey residential building on this site for CSA-B44 upgrade. Scope of work: - Reprogram existing addressable single stage fire alarm system and modify existing fire alarm annunciator to show additional automatic emergency elevator recall zones. - Install new relays and reprogram existing addressable FAS initiation devices to allow for activation of the automatic emergency elevator recall sequence. - Programming of Elevator Recall and FEO functions. ******THIS PERMIT HAS BEEN ISSUED UNDER THE REQUIREMENTS OF VBBL 2019 AND REVIEWED DURING THE 2020 COVID-19 PANDEMIC CRISIS. ******** Building Review Branch Notes: · $15,872
no contractor listed Issued -
2019-03-13
To installation of a new fire alarm system as per City staffns and audible horn strobe combination devices at the exit doors on each floor starting on the main floor up to the 10th floor. Riser conduits to go up the existing stairwells to access each floor. A new Mircom fire alarm panel to be installed in the main lobby adjacent to the elevators. Some coring through floors will be required. Electrical drawings are attached. AL-2018-00249 VBBL 3.4.4.4(1)(b) · $60,000
OCEAN PACIFIC RESTORATION Issued
The City of Vancouver publishes permits when they are issued and does not show whether the work was completed, so every Vancouver permit shows as Issued with its issue date.
Email alerts and sign-up aren't available yet. Everything on these pages is free to use without an account. Questions: [email protected]
Recent permits in West End
#650 - 6th floor Interior alterations to provide improvements to this existing vacant office space on the 6th floor (#650) of this existing commercial building on this site. Scope of work; remove 2 walls. Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · Makcom Construction Ltd2026-10-30
#600 - 6th floor - ( demising into #600 and #660) Interior alterations to the 6th floor to demise unit 600 (to be #600 and #660) and provide improvements to #660 in this existing commercial building. Scope of work; demo to north half of suite and construct a demising wall, and partition walls for new layout. Electrical, plumbing, & Sprinklers to suit. Energy checklist is currently no longer required with your Building Permit (BP) application. Some supporting documents are still required at BP stage, specifically Envelope and HVAC, if applicable. Service Water Heating and Lighting supporting documents, if applicable, must be submitted with your related trades permits (e.g. electrical and plumbing). · Makcom Construction Ltd2026-10-30
Unit 600: Interior alterations to remove the existing convenience stair between 5th & 6th floor in this existing commercial building. BRB notes: -To infill the existing convenience stair opening with new structural floor assembly maintaining fire separation with 2h F.R.R. - Separate building permit and sprinkler trades permit will be required for other tenant improvement works on the 6th floor for any alterations/reconfigurations of floor space. - This application is reviewed under VBBL 2025. · Aura Office Environments Inc2026-10-30