Permit GopherAlberta and B.C. property, permit and zoning records

13111 Meridian Street NE, Edmonton

An address in Clover Bar Area, Edmonton, zoned DC2 (Site Specific Development Control Provision). 14 building permits are on file, most recently “To construct Interior Alterations (new steam line venting, transformers and electrical pa…” (issued 28 January 2026). 7 development permits are on file too. The City's 2026 assessed value for the 6 accounts at this address is $11,489,500. The City of Edmonton does not publish contractor names.

Zoning
DC2 · Site Specific Development Control Provision
Neighbourhood
Clover Bar Area
Permits on file
14
+ 7 development
Assessed value (2026)
$11,489,500
6 accounts, total
Owner names are not part of the City's open data and are never shown. Sold prices are not municipal open data and are not shown. Assessed value is the City's estimate for property tax, not a sale price.
Aerial photo around 13111 Meridian Street NE, with the address marked
Address point from the City of Edmonton's open data. Aerial photo: City of Edmonton, 2025. Contains information licensed under the Open Government Licence – City of Edmonton.

Neighbourhood profile

From the 2021 Census, for the small area around this address that Statistics Canada calls a dissemination area (48112493, 25 people). Statistics Canada draws these areas; they are not the City's neighbourhoods.

People
25
Households
not published
Median age
not published
Median household income (2020)
not published
Own their home
not published
Edmonton: 64%
Average household size
not published
Under 15
not published
65 and over
not published
Income in the 2021 Census is for the year 2020. Statistics Canada rounds counts and does not publish some figures for very small areas.

Permit history

  1. 2026-01-28 To construct Interior Alterations (new steam line venting, transformers and electrical panel) to an existing industrial building (Edmonton Waste Management Center). · $35,000
    contractor not published by the City
    Issued
  2. 2025-04-08 To construct Interior Alterations (slab refurbishment) to an existing industrial building. "Large Dome" · $500,000
    contractor not published by the City
    Issued
  3. 2024-01-08 To construct Interior Alterations to an existing Materials Recovery Facility (electronics waste recycling facility). Renovate existing enclosed Mezzanine and renovating the main floor area below mezzanine including new washrooms. 4 RTUS. ” Quantum Lifecycle” · $128,510
    contractor not published by the City
    Issued
  4. 2023-08-14 Modifications to the existing fire alarm system. --"The Edmonton Waste Management Center"-- · $12,000
    contractor not published by the City
    Issued
  5. 2022-10-24 To construct an accessory building (Compressor building) to a Major Impact Utility Service (Enerkem Alberta Biofuels). · $1,300,000
    contractor not published by the City
    Issued
  6. 2021-01-19 To complete Interior Alterations (construct partition walls, install doors, altering mezzanine area) and Exterior Alterations (install two new doors), to the Small Dome building. - Edmonton Waste Management Centre NOTE: Trade Permits to reference "REVISED (Feb 25, 2021) Scope of Work" letter · $1,300,000
    contractor not published by the City
    Issued
  7. 2020-02-25 To construct interior alterations to an existing building. Change use from F1 to F3. Large (East) Dome for storage of pick-ups, loaders, tractors, skid steers, ect. Small (West) Dome used for storage of parts and mechanical equipment including motors, conveyor bellts, bearings, electrical components, ect. which is the planned continued use. The office block and mezzanines are not being re-purposed, and the mezzanines are planned to be used for connection/access only. · $532,611
    contractor not published by the City
    Issued
  8. 2018-01-08 To construct an accessory biofuels facility Service Building (houses an H2 & CO Compressor). · $120,000
    contractor not published by the City
    Issued
  9. 2014-09-16 To construct a waste water treatment facility for the Waste-to-Biofuels Facility (Edmonton Waste Management Centre) · $524,000
    contractor not published by the City
    Issued
  10. 2014-09-16 To construct a Waste-to-Biofuels Facility (Edmonton Waste Management Centre) "Biomass Storage Building". · $1,500,000
    contractor not published by the City
    Issued
  11. 2014-09-10 To construct a Biofuels Facility (Edmonton Waste Management Centre) - Compressor Building · $467,000
    contractor not published by the City
    Issued
  12. 2014-09-10 To construct a Biofuels Facility (Edmonton Waste Management Centre) - Maintenance Building · $265,000
    contractor not published by the City
    Issued
  13. 2010-05-14 To construct a general industrial building (Greys Paper & Glass Recycling Plant). This project consists of 2 domes with a central link area. The complex is divided by a 4 hr firewall seperating the large dome into Building 1, and the central link area with the smaller dome, into Building 2. The large dome consists of a single storey, paper recycling facility with a viewing mezzannine. The small dome contains a single storey, glass recycling facility. The central link is a 2 storey office admin area with a roof top patio and 1 RTU. · $3,000,000
    contractor not published by the City
    Issued
  14. 2010-01-26 To construct a Structural Frame for a general industrial building / 2 Monolithic Dome type bldgs w/ central connection link, large dome separated from link and smaller dome w/ 4hr. firewall. Link is a 2 storey office area w/ roof top patio, large dome is paper recycling plant while smaller dome is glass recycling plant. (Grey's Paper Recycling Plant - Materials Recovery Facility)
    contractor not published by the City
    Issued

Development permits

The City's decisions on what may be built or how the property may be used, which come before the building permit. The City publishes no applicant for these.

  1. 2022-05-26 To construct an accessory building (Compressor building) to a Major Impact Utility Service (Enerkem Alberta Biofuels).
    Garage, shed or deck Major Development Permit · City file 429117818-002
    Approved
  2. 2021-07-08 To construct a Major Impact Utility Service building with exterior alterations (access and landscaping). (TEMPORARY - 2 YEARS)
    New building Major Development Permit · City file 376835139-002
    Approved
  3. 2021-01-06 To Change the Use from General Industrial Use to a Professional, Financial and Office Support Service / General Industrial Use (Research and Development Work Spaces) and to Construct Exterior Alterations (New Overhead Doors) and to Construct Interior Alterations
    Change of use Major Development Permit · City file 381243579-002
    Approved
  4. 2020-05-29 To install a Minor Digital On-premises Fascia Sign (1.8m x 3.6m facing S) (EDMONTON WASTE MANAGEMENT CENTRE)
    Sign Sign Permit · City file 356791771-001
    Other
  5. 2019-11-22 To Change the Use from a Major Impact Utility Service to a General Industrial Use (Storage)
    Change of use Major Development Permit · City file 344400859-002
    Approved
  6. 2017-06-29 To construct an Accessory Biofuels Facility building (houses an H2 & CO Compressor).
    New building Major Development Permit · City file 098424077-009
    Approved
  7. No description
    Other Major Development Permit · City file 631591942-002
    Other

Email alerts and sign-up aren't available yet. Everything on these pages is free to use without an account. Questions: [email protected]

Recent permits in Clover Bar Area

14604 33 Street NE
To install a Renewable Energy Device (freestanding Solar Collector, 12.5m x 3.4m @ 4.0m in Height). · contractor not published by the City
2026-10-20
12920 33 Street NE
Demolition of accessary building. "ATCO trailer" · contractor not published by the City
2026-09-10
11821 28 Street NE
To construct Exterior Alterations ( new overhead door in North elevation) to an existing General Use Industrial building. · contractor not published by the City
2026-08-21
Something wrong on this page? Tell us and we'll check it against the City's records.