Help: This address page
What this page does
This page shows what the city's open data records for one address: the zoning and what it means, the neighbourhood, every building permit on file and, where the city publishes it, the assessed value. It also shows the property on the city's aerial photo or a drawn plan, a 2021 Census profile of the small area around it, and recent permits nearby. Free, no account. Owner names and sold prices are never shown; the assessed value is the city's estimate for property tax, not a sale price.
How to use it
- Read the top lines for the summary: zoning, neighbourhood, number of permits and assessed value.
- Use + and − on the plan to zoom in and out.
- Scroll to Permit history for every permit on the lot: what was done, when, by which company, the value and the status.
- Click a nearby permit to open its address, or This week's permit digest → for the whole city.
- Something looks wrong? Use the Tell us link at the bottom and we'll check it against the city's records.
9500 100 St SE, Calgary
An address in Residual Ward 12 - Sub Area 12a, Calgary, zoned DC,I-C,I-G,S-SPR,S-UN (Direct Control / Industrial - Commercial / Industrial - General / Special Purpose - School, Park and Community Reserve / Special Purpose - Urban Nature). 40 building permits are on file, most recently “Carbonova Nanofibre Commercial Development Unit” (issued 26 October 2026). The City's 2026 assessed value is $93,216,585.
Neighbourhood profile
From the 2021 Census, for the small area around this address that Statistics Canada calls a dissemination area (48062402, 312 people). Statistics Canada draws these areas; they are not the City's neighbourhoods.
Permit history
-
2026-10-26
Carbonova Nanofibre Commercial Development Unit · $100,000
no contractor listed Issued -
2026-08-11
CO2 Capture Unit · $200,000
no contractor listed Closed -
2026-05-14
Fire alarm repair · $100,000
JOHNSON CONTROLS CANADA Issued -
2023-05-26
fire alarm alteration · $25,000
TARPON ENERGY SERVICES Closed -
2021-03-04
Shepard Energy Centre - CT1 Major - Temporary Storage · $30,250
WARNER SHELTER SYSTEMS Issued -
2021-02-10
Shepard Energy Centre - Fire Detection System Reliability · $75,000
ENMAX Closed -
2020-06-02
Temporary X-Prize Scale Up Building 1 · $7,595
no contractor listed Issued -
2020-05-19
New - ACCTC Capture Plant Buildings · $127,000
no contractor listed Closed -
2020-04-03
Temporary Intermodal Storage - Group F3 - X-Prize Competition · $7,361
no contractor listed Issued -
2020-02-10
Temporary office trailer - C2CNT · $10,000
no contractor listed Closed -
2020-02-06
New - Group F2 - Storage Building · $10,000
no contractor listed Closed -
2020-01-22
New Temporary 1-storey building, Group F3 · $500,000
no contractor listed Closed -
2020-01-08
New - Temporary Office Trailer · $10,000
no contractor listed Closed -
2019-11-25
New Temporary 1-storey building, Group F3 · $145,000
no contractor listed Closed -
2019-01-22
New Industrial steel building for Enmax. · $400,000
no contractor listed Closed -
2018-11-27
C2CNT STORAGE CONTAINER (new) · $13,000
no contractor listed Closed -
2018-02-13
CO2 COMMERCIALIZATION TEST CENTRE (new) · $51,000
no contractor listed Closed -
2017-09-25
Electrical House Building at CO2 Commercialization Test Centre · $126,000
no contractor listed Closed -
2015-06-05
Industrial Water filtration building · $355,000
no contractor listed Closed -
2015-05-19
Temporary Tents - Enmax Shepard Grand Opening · $3,000
no contractor listed Closed -
2015-01-22
Racking installed · $4,500
no contractor listed Closed -
2014-10-16
Pre-manufactured steel building for lubricating oil storage. · $70,000
no contractor listed Closed -
2014-10-16
Relocation on site of a fabric/steel structure. · $75,000
no contractor listed Closed -
2013-12-19
Racking · $2,500
no contractor listed Closed -
2013-07-10
New Utility Buildings · $870,000
KBV SHEPARD POWER PARTNERS Closed -
2013-04-01
New Power Generation Facility · $400,000
MAKLOC BUILDINGS Closed -
2012-07-12
New Power Generation Facility · $488,816
KBV SHEPARD POWER PARTNERS Closed -
2012-05-22
New power plant · $28,475,900
KBV SHEPARD POWER PARTNERS Closed -
2012-04-24
Power Generation Facility Admin Building · $4,200,000
no contractor listed Closed -
2012-04-13
Shepard Energy Centre · $75,000
no contractor listed Closed -
2012-02-23
New - Temoporary Offices · $150,000
no contractor listed Closed -
2012-02-01
Temporary Breezeway Installation · $25,000
no contractor listed Closed -
2011-12-15
Maintenance shop · $131,500
KBV SHEPARD POWER PARTNERS Closed -
2011-12-12
Temoporary Offices - Owners' Office · $120,000
KBV SHEPARD POWER PARTNERS Closed -
2011-08-12
2 New Temparary Structures · $340,000
KBV SHEPARD POWER PARTNERS Closed -
2011-08-08
Commercial Project - Temporary Structures (2) · $113,700
no contractor listed Closed -
2011-07-20
Temporary construction trailers · $25,500
KBV SHEPARD POWER PARTNERS Closed -
No description
no contractor listed In review -
Temporary X-Prize Scale Up Building 2
no contractor listed Closed -
C2CNT - 30'-0" x 20' - 0" Storage Tent · $3,000
no contractor listed In review
Email alerts and sign-up aren't available yet. Everything on these pages is free to use without an account. Questions: [email protected]
Recent permits in Residual Ward 12 - Sub Area 12a
Interior alteartions · 1876209 ALBERTA2026-10-02
Racking only · no contractor listed2026-08-13
Interior alterations · SCOTT BUILDERS2026-07-07